Monday, April 1, 2019
Issues in the Construction of the Scottish Parliament
Issues in the whirl of the stinting fantanIntroductionThis report int give the axes to retort how a national iconic excogitate turned into a hugely expensive and politic eithery embarrassing fiasco? (Fortescue, 2004) by analyzing the reasons that led to fit, constitute overrun and part distinguish in manifestation of new frugal fan tan Building. This report has utilized the researches available on the internet, canvassors report and nigh other articles available from varied sources. This report pull up stakes start by entering to the background of stinting fantan stray and will continue by discussing the reason for stops and constitute amplifications, spot of the project centering and at the force out concluding the lessons learned from this project. The reason for selection of this project is that the Scottish Parliament mental synthesis was estimated to be completed in 40m barely finished at over 400m which is an interesting parameter to study (BBC, 2004) .Background to the Scottish Parliament ProjectAfter the referendum in 1997, Scottish parliament was established as a devolved legislature by Scotland Act 1998. Thereafter, Donald Dewar, Secretary of Scotland state adjudicated to live a purpose reinforced facility to accommodate the Parliament in the Edinburgh city. After having a chaotic journey to completion, Scottish parliament labyrinthine was inaugurated on 9 Oct 2004 by Queen Elizabeth II. Remarkable features of the complex inhabit of leaf-shaped pretendings, flipped over boat shaped roof, a grass-roofed division meeting into side by side(predicate) parkland and gabion walls made from the st superstars. All over the construct at that place argon various repeated motifs. Scottish parliament is a complex construct comprising of new and old buildings such as Dewar room, Canon gate building, Debating chamber, tend lobby, MSP building, Media tower, Main hall, Tower building, and Queensberry house. All of these buildings wer e renovated or constructed as per Architects vision. High end materials like Granite, Cattiness Stone, Oak Timber, Sycamore Timber, Steel Glass and stain was used in the construction. Detailed environment and sustainability study was carried out which sustain that propose built complex is environment friendly (Fraser, 2004).Brief epitome of the Project Road to HolyroodSite pickaxeTo begin with, Edinburgh City Council offer upd a long list of 27 sites in Edinburgh. In September 1997 officials unmindful listed three leading options two new build options, either at Leith or Haymarket, or adapting and developing the existing St Andrews residence building (old kingly last school). At this level, an engineer Jones Lang Wootton was engaged by the Scottish spotlight to viably evaluate the acquisition monetary value of the gradeed sites. Measurements of environmental issue and traffic issue were in addition considered at this point. Haymarket was never considered as preferred op tion and officials sensed real hostility in Edinburgh to house the Parliament anywhere chuck out rallyly thus reducing the chances of Leith ( canvassor public, 2000).The Holyrood site was non considered at this stage as it was occupied by Scottish and Newcastle brewery and was anticipated that it would not be completed inwardly the required deadline. However, an accidental meeting of a elegant servant on train with an official of Newcastle and subsequent negotiations resulted in the company demonstrating that they would evacuate the site in earlier 1999. As a consequence, on 8th December Holyrood was short-listed, and function and cost viability studies undertaken. Davis, Langdon and Everest (DLE) , bell Consultants were commissioned to provide initial cost estimate for proposed sites and the Holyrood site was selected in other(a) 1998 from the shortlist based on the following cost estimate ( studyor General,2000).Design excerptionOnce, the location was finalized the S cottish Office announced an international competition to clear a inclinationer for a new-fangled building to accommodate the parliament finished a competitive selection procedure. The competition was suitably setup with a press release on 26 January 1998. The final design teams named on 7th May 1998 providing the project cost as being in the range of 50 million excluding VAT (Fraser, 2004).Under the chairmanship of Dewar, a design committee was allotted to choose from a shortlist of designer. Conceptual designs were cost and displayed for humans to view and provide their opinion. Feedback from the public depicted that the Catalan interior decorator Enric Miralles designs were one of the most popular. The design team considered public opinion on the designs, and on 6 July 1998 the Enric Miralless design was selected, with work being awarded to a Spanish Scottish design company namely EMBT/RMJM (Scotland) Ltd, exclusively created for the project. Construction forethought admini stration of procurement was adopted and BLL was appointed as construction coach. In June 1999, construction commenced, by demolishing the Scottish and Newcastle brewery and opening the foundation garment work (The royal society of Edinburg, 2001).Journey of EstimateThe construction of the Scottish Parliament Complex generated controversy in some(prenominal)(prenominal) aspects. Spiraling costs and the use of public capital to fund the project dedicateed most controversy. By early 2004, the project was estimated to be 430m, some ten judgment of convictions higher. In my opinion it is not fair to compare final figure with initial figure of 10m as it was never an estimated price but an indicative one (Fraser, 2004).Time delay and cost overrunFrom the beginning, the complex and its construction beget been controversial. For instance, Auditor General of Scotland expressed in the recent history of Scotland there has not been public building project as complex or as difficult to ret ort as the Holyrood Project (Prasser, S., n.d.). Almost all aspect such as location, design, architect, construction steering company, project manager all have been criticized by different factions namely, politician, media and general public. Due to complexity of the project, it is genuinely difficult to single out one reason for delay and cost overrun but infect it was compound and interaction of legion(predicate) chemical factors that resulted in delay and cost overrun (Fraser, 2004).Location Selection of Holyrood to be the seat of parliament has contributed to delay and cost overrun. Holyrood was not an easy rural area to work delinquent to the approach and being located in be area. The selection of Holyrood added 4.5m to the project being the cost for site acquisition and clearing. As the table1.1 (Fraser, 2004) shows, according to the costing through by DLE Holyrood was not economically attractive.Design and Design Development FactorMain cause of the delay to the proj ect was from Sept2000 due to the production of fine design variations and the late allow of information during the construction process (Auditor General, 2004). Construction started in June1999 but head D design was approved after a year. Everyone anticipated that this will put an end too uncertainly and provide some part of anchorage for the project but it did not happen. The project was densely populated, extraordinary(predicate) and complex and was pitted against tight deadline. In some cases, trade contractors were obligated for part design but twain the architects and some trade contractors failed to deliver some critical elements on succession. Design development process added other 80m to the cost of project. It is a process of bringing approved design to detailed design. This process runs parallel to Tendering and award of work packages and subsequent work on site. From 2000 onward, client didnt change its requirements significantly but the cost of bringing picture design to reality escalated (Black, 2004).Increase in area after several(prenominal) revisions and new requirement were incorporated, total area r to each oneed from 16000.00 m2 to 31,000.00 m2 resulting in an increase of 47% and consequently effecting entry and cost of the project. Building users brief prepared by the authorities substantially underestimated the requirements which resulted in various revisions and thus increase in area. For instance, Mr. Stewart said that the original estimate was absolutely, too optimistic for a public building of this nature (Fraser, 2004). The experience and expertise in construction wariness was not fully developed and was not present in the early stages of development.Procurement vehicle In 1998, Civil servants opted for fast track system known as construction management form of procurement to build the parliament complex (Fraser, 2004). It works by fragmenting complete job into several small packages that are awarded, monitored and desi gned independently of one another. Its advantage is that the general design doesnt have to be complete at the start of building works. In this form of contract, insecurity stays with the client, which is responsible for(p) for management of each individual work package-in this case around 60. However, after keeping in mind importance and urgency of the project, construction management procurement was the exclusively viable option available. For instance, Harry Thorburn articulated, The reality is that construction management was the yet contract option for a client wanting to make an early start on a project that was still at the design concept stage (Fortescue, S. 2004).Communication and coordination was another issue which added to the foes of already dissipated project. Fraser (2004) reports that there was a lack of communication, coordination and understanding among stakeholders, for example, resolution of galore(postnominal) design issues was delayed due to misunderstan ding and lack of communication between RMJM EMBT.Landscaping is although minor part of general figure, still it reflects reverse of system. Cost of landscaping amounting to 14 m came to the surface and was added when the project was well afoot(predicate) during autumn 2001 (Fraser, 2004).Schedule Time-table for completion by project management was very demanding and idealistic rather than realistic. Construction manger consistently tried to get through the set target but failed. According to Auditor Generals report (2004), schedule set in Sept 2000 for completion by December 2002 was in all likelihood unachievable. Proper EU guidelines and procedures were not followed for appointment of Bovis Lend and Lease as construction manager. BLL was not the lowest, yet they were awarded. BLLs contract was supposed to be converted to Lump rundown after finalization of cost plan but was not done. Conversion of fees would have provided a powerful incentive to Bovis to oblige maximum rigo r in relation to cost suss out. No system was devised and implemented neither for deed measurement nor for cost insurance coverage, analysis and financial control.Queensberry House proved to be the most costly item, in harm of cost per square meter (Fraser, 2004). However, Queensberrys cost was comparatively minor in consideration of the full cost of the Project at completion. Golden triangle of quality time and cost was ignored and quality was preferred against time and cost, time was preferred against cost. The undue importance given to time and quality resulted in escalated cost.Security issue and 9/11 factor also played an important role in delay and spiraling cost of the project. Fraser in his enquiry agrees that security bill amounted to 29.11. Design of anti-blast measures causes a sum of 17.54m and delay associated with blast causes additional sum of 11.57m. Another major factor to be recognized was constructing a very complex, unusual building, visionary computer arc hitecture was difficult to bring to reality. The Debating chamber roof, for example, was an extremely challenging task both for designers and builders (Fraser, 2004). Proper risk analysis and cost management studies were not done. At the early stage of decision devising, no independent professional project management company was inculpated to advise the client.Role of Project wayRole of Project management is to deliver the project on time, within budget and with acceptable quality (Fraser, 2004). In this case, Project management provided an special complex of high quality but failed miserable in context to cost and time.Black (2004) criticized performance of the project management or officials responsible for delivering the project. Decision making process and control over project was not clearly recognized along with lack of leadership. Normally project theatre director is responsible for leadership and control, client delegates the authority to project director to render the project. Here, project director should have had clear responsibility in making decisions on balancing time, cost and quality/performance of the project. Auditor General (2004) af fast(a)ed that the client (the Parliament) did not clearly establish leadership and control of project. Leading parties could not agree on cost plan which was a missing link in effective project management, a conscription plan was made in late 2000, that was an indicator of the costs rather of available estimate of the cost.Under construction management, design was vague and in nice initially, therefore the risks remained with the client (Fig 1.1). Project management selected a high risk travel guidebook but failed to manage it properly. Risk accounting was insufficient in early stages and there was no quantified allowance for risk facing the project. initially project management did introduce a process for quantifying risk and conducted some reviews but the general approach was to accept the cost incr ease and increase in the forecast as risk materialized. No system or forceful action was adopted to reduce the increase in cost (Fraser, 2004).Project management did not fully implement cost reporting and financial controls. Regular reporting of the total estimated costs of the project yet started in July 2003(Black, 2004). Earlier financial reporting was neither comprehensive nor regular. Once, the overall budget constraint of 195m was removed by Parliament in June 2001, management did not establish an alternative budget which gave them liberty to achieve high quality and tight deadlines without due considerations of cost implications (Black, 2004 Fraser 2004).ConclusionProject management plays an important role in the success of mega and prestigious projects. Construction of Scottish parliament has put a negative mark on the role of project management. Delay and cost overrun of the project cannot be attributed to the failure of project management only, Fraser (2004) in his quer y stated that it was the result of systematic failure and it is difficult to single out one villain. Also, there were several mistakes but the biggest one was involved in Procurement system. They were interconnected, increased exponentially, and had a rippling effect which was visible all throughout the period of construction. scorn of all the problems, Scotland has got an architectural gem its an iconic building representing the land. In fewer years, the mickle of Scotland will be as proud of it as the people of Sydney are of Opera House, which was also an example of project failure when it was built (Australian Government Department, 2006 Mosaic Projects, n.d.).The entire project should have agreed project budget and proper set of performance indicators. Proper benchmarking should be done to measure the performance. If, competition is commissioned for selection of design, proper evaluation of pre qualification moldiness be done and compatibility of working cultures should be co nsidered. While selecting the design, oversight should be paid to cost and execution problems that may arise due to complexity of design.Procurement route must(prenominal) always be elect with care coupled with comprehensive evaluation.Construction management procurement route should be used rarely for public projects. Before construction starts adequate time should be available for the planning stage. As Fraser (2004) reports that investing time initially, to develop complete definitions reduces the chance of changes by and by. Good planning will involve (a) right sequence of construction to avert delays and extra costs, (b) risk management (c) using value management to evaluate the role of each element of the construction processes (Black, 2004) (d) Selection of proper planning system There must always be sufficient time for procurement to allow the clients requirements to be adequately define so that it may obtain fixed and firm prices for the work in a competition (Black, 2 004). In all projects, performance payment incentives system should be initiated for contractors to perform against targets for quality, time and cost.Clearly defined duties and single point of leadership with explicit authority and responsibility should be ensured. Strong system of reporting and transparent channels of communication must be devised.It is essential that full contracts, guarantees and bond should be secured to prevent the risk. aboriginal involvement of contractors in design phase might help in solving the problems later on. Concurrent engineering should be carried out to avoid complications during execution. Safety measures needs to be a considered as an integral part. In this particular case, no one would have anticipated the impact of 9/11. So it is better to have some contingency plan in place to tackle unforeseen events.BibliographyAuditor General (2004). care of the Holyrood building project prepared for the Auditor General for Scotland Project overview, th e reason for later delivery and increased costs, project management and control. Chapters 1-5., pp 1-92. operational from http//www.audit-scotland.gov.uk/docs/central/2004/nr_040629_holyrood_project.pdf Accessed second April 2010.Auditor General (2000). The new Scottish Parliament building an enquiry of the management of the Holyrood building project prepared for the Auditor General for Scotland. getable from http//www.audit-scotland.gov.uk/docs/central/2000/nr_000919_new_parliament_building.pdf Accessed 3rd April 2010.Australian Government Department (2006). Sydney Opera House Nomination by the govt of Australia. on hand(predicate) from http//www.sydneyoperahouse.com/uploadedFiles/About_Us/Ad_Hoc_Information_Pages/WorldHeritageNominationDocument.pdf Accessed 8th April 2010BBC (2004). Timeline Holyrood. purchasable from http//news.bbc.co.uk/1/hi/scotland/3210729.stm Accessed second April 2010.Black, R. (2004). Presentation by the Auditor General for Scotland, Robert Black to the Audit Committee of the Scottish Parliament, on his report, Managing of the Holyrood building project Available from http//www.audit-scotland.gov.uk/docs/central/2004/nr_040629_holyrood_projec_statement_pr.pdf. Accessed quaternate April 2010Black R. (2004) Audit Scotland. Available from http//www.audit-scotland.gov.uk/publications/pdf/2004/04pf07ag.pdf Accessed 4th April 2010Black R. (2004) Audit committee official report 29 June 2004 Available from http//www.scottish.parliament.uk/business/committees/audit/or-04/au04-1402.htm Accessed 4th April 2010Edinphoto (n.d.). Scottish Parliament Complex at Holyrood. Available from http//www.edinphoto.org.uk/0_edin_t/0_edinburgh_transport_buses_terminus_36_holyrood_024373.htm Accessed second April 2010Fortescue, S. (2004). The 431 million question. Available from http//www.pennwood.org.uk/Level%20Four/L402/Holyrood%20example.pdf Accessed 3rd April 2010Fortescue, S. (2004). The 431 million question release management. Available from htt p//www.supplymanagement.com/analysis/features/2004/the-431-million-question/ Accessed 3rd April 2010Fraser, R. H. L. (2004). A Report by the Rt Hon headmaster Fraser of Carmyllie QC on his Inquiry into the About Holyrood Project. SP Paper 205. Available from http//www.scottish.parliament.uk/vli/holyrood/enquiry/sp205-00.htm Accessed second April 2010.Fraser, R.H.L. (2004). Events Prior to 1 May 1997. Available from http//www.scottish.parliament.uk/vli/holyrood/ question/sp205-02.htm. Accessed 2nd April 2010Fraser, R.H.L. (2004). uninfected Paper to the Passing of the Scotland Act 1998. Available from http//www.scottish.parliament.uk/vli/holyrood/inquiry/sp205-03.htm Accessed 2nd April 2010Fraser, R.H.L. (2004). Selection of the Holyrood Site. Available from http//www.scottish.parliament.uk/vli/holyrood/inquiry/sp205-04.htm Accessed 2nd April 2010Fraser, R.H.L. (2004). Appointment of the Architect Available from http//www.scottish.parliament.uk/vli/holyrood/inquiry/sp205-05.htm Acc essed 2nd April 2010Fraser, R.H.L. (2004). The Evolution of the Building User Brief. Available from http//www.scottish.parliament.uk/vli/holyrood/inquiry/sp205-06.htm Accessed 2nd April 2010Fraser, R.H.L. (2004). Construction charge. Available from http//www.scottish.parliament.uk/vli/holyrood/inquiry/sp205-07.htm Accessed 2nd April 2010Fraser, R.H.L. (2004). The Appointment of the Construction Manager. Available from http//www.scottish.parliament.uk/vli/holyrood/inquiry/sp205-08.htm Accessed 2nd April 2010Fraser, R.H.L. (2004). Project Management 1998 to 1 June 1999. Available from http//www.scottish.parliament.uk/vli/holyrood/inquiry/sp205-09.htm Accessed 2nd April 2010Fraser, R.H.L. (2004). The Project from Handover to February 2000. Available from http//www.scottish.parliament.uk/vli/holyrood/inquiry/sp205-10.htm Accessed 2nd April 2010Fraser, R.H.L. (2004). Early 2000 and the arrangement of the Holyrood Progress Group. Available from http//www.scottish.parliament.uk/vli/holyro od/inquiry/sp205-11.htm Accessed 2nd April 2010Fraser, R.H.L. (2004). The Holyrood Project June to December 2000 -Stage D The Cost Plan. Available from http//www.scottish.parliament.uk/vli/holyrood/inquiry/sp205-12.htm Accessed 2nd April 2010Fraser, R.H.L. (2004). The Project from Late 2000. Available from http//www.scottish.parliament.uk/vli/holyrood/inquiry/sp205-13.htm Accessed 2nd April 2010Fraser, R.H.L. (2004). Planning, Queensberry House and the Role of Historic Scotland. Available from http//www.scottish.parliament.uk/vli/holyrood/inquiry/sp205-14.htm Accessed 2nd April 2010Fraser, R.H.L. (2004). Programming and Design Delay- Factual Background- Construction Manager. Available from http//www.scottish.parliament.uk/vli/holyrood/inquiry/sp205-15.htm Accessed 2nd April 2010Fraser, R.H.L. (2004). Security Issues. Available from http//www.scottish.parliament.uk/vli/holyrood/inquiry/sp205-16.htm Accessed 2nd April 2010Fraser, R.H.L. (2004). The Holyrood Project from surrender 20 03 Onwards. Available from http//www.scottish.parliament.uk/vli/holyrood/inquiry/sp205-17.htm Accessed 2nd April 2010Meredith, J.R. Mantel, S.J. (2006). Project management a managerial approach 6th edition. John Wiley sons, New York.Mosaic Projects (n.d.). Avoiding the successful failure. Available from http//www.mosaicprojects.com.au/PDF_Papers/P046_Successful_Failure.pdf Accessed 8th April 2010.Prasser, S. (n.d.). Parallels with Overseas Experience The Holyrood Building Project, Scotland Overcoming the White Elephant Syndrome in whacking and Iconic Projects in the Public and Private Sectors. Available from http//epress.anu.edu.au/anzsog/imp/mobile_devices/ch05s07.html Accessed 4th April 2004Project Management Institute (2004). A guide to Project Management Body of Knowledge third edition (PMBOK Guides). Project Management Institute. Newtown Square. USA.Philadelpia.Roberts, D (2003). MSP says Holyrood builders are left idle Available from http//www.scotsman.com/politics/MSP-sa ys-Holyrood-builders-are.2459894.jp Accessed 4th April 2010. affix management.com (2004). The 431 million question. Available from http//www.supplymanagement.com/analysis/features/2004/the-431-million-question/ Accessed 3rd April 2010Scottish Parliament, (2001). The Scottish Parliament building. Available from http//www.scottish.parliament.uk/business/research/pdf_res_notes/rn01-64.pdf. Accessed 5th April 2010The royal society of Edinburg (2001). engine room the Scottish Parliament building. Available from http//www.royalsoced.org.uk/events/reports/2000-2001/rae_01.pdf Accessed 4th April 2010The Scottish Government (2007). The political relation economic strategy. Available from http//www.scotland.gov.uk/Resource/Doc/202993/0054092.pdf. Accessed 3rd April 2010Westland, J. (2006). The Project Management Life Cycle. London Kogan Page.
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment